RA 9184 | Approved Budget for the Contract (ABC) | Variation Order | Program of Works

Q: Ask ko po sana sa ganitong scenario sa bidding: Original contract price: 5M Revised contract price after variation: 5.5M ABC: 5.3M POW & PR amount: 5.8M Yung question ko po still Allowed pa rin po ba to na ung revised contract price na 5.5M nag exceed na sa ABC (5.3M) pero pasok pa sia […]

Continue Reading